Conveying Pipe Line, Water Treatment and Pump Station Project in Mirabad

Conveying Pipe Line, Water Treatment and Pump Station Project in Mirabad

Name of project :

Conveying Pipe Line, Water Treatment and Pump Station Project in Mirabad

Employer :

Water and Wastewater Company in Chaharmahal and Bakhtiari Province

Supervisor :

Deputy of Engineering and Development of Water and Wastewater Company in Chaharmahal and Bakhtiari Province

Location :

Mirabad, Chaharmahal and Bakhtiari Province, Iran

Status :

Finished in 2008


 

Main Volumes of the Project

Excavation

50.000

cubic meters

Fill

5.000

cubic meters

Concrete

3.200

cubic meters

Steel Piping with nominal diameter of 400 millimeters

5

Kilometers

Mold

4.200

square meters

Bar

210

ton

Steel

20

ton

Asphalt

5.000

square meters

Total area of non-industrial building

700

square meters

shahrekord-refinery-1.jpg
shahrekord-refinery-2.jpg